St. Peter's 'Growing on the Rock' Project

Following a needs and planning study, the congregation at St. Peter's United in Sudbury approved preliminary plans for an addition and renovations to the church in 2007. Central features of the changes are an elevator, serving all three church levels, a new barrier free washroom on the lower level and enlarged entrance and narthex areas as well as a new kitchen and several new offices and meeting rooms.

A Growing on the Rock financial campaign was held in early 2008 and contributions and pledges currently are close to the $ 600,000 mark. After a period of tendering and consequent adjustment of the plans to match the funds raised, a contract with a project management company was signed in July 2009 and a ground turning and blessing ceremony was held in September. The construction work is scheduled for completion by the end of January 2010.

 

1-Groundbreaking

In the photo, St. Peter's minister, Rev. Dawn Vaneyk (centre) is shown at the ground turning with congregational representatives from the building committee, the youth, the UCW, and members with accessibility challenges.

 

Our Building Project includes:

  • An elevator serving all three church levels.
  • A new barrier free washroom on the lower level.
  • A new entrance, cloakroom and enlarged lobby or narthex.
  • New administrative offices.
  • A new nursery beside the sanctuary.
  • A new kitchen (on the lower level)
  • New electrical & heating systems.
  • Upper parking lot changes to allow barrier free entry at the main entrance doors.
 
Project Details

Cost: approximately $ 600,000, supported by a church fund raising campaign.
Duration: project start-Sept. 23, 2009 - completion-end of Jan. 2010
Architect: Perry & Perry
Construction Management: Hawkey Church Management Inc.

The project will also improve our hosting of concerts and other community events.

Below are some progress photos of the work underway.

2-ArchitectsDrawing

Architect's Concept Drawing

 

3-Week1

Week of September 13 - Ready to start

 

4-Week2

Week of September 20 - Start of construction Sept. 23

 

5-Week3

Week of September 27 - Rock breaking

 

6-Week4

Week of October 4 - Footings poured and sand filled

 

7-Week4b

Week of October 4 - Wall forms installed

 

8-Week5

Week of October 11 - Foundation complete

 

9-Week6

Week of October 18 - Waterproofing installed

 

10-Week7

Week of October 25 - Floor slabs delivered

 

11-Week7b

Week of October 25 - Upper floors complete

 

12-Week8

Week of November 1 - Lower level kitchen area

 

13-Week8b

Week of November 1 -
Framing on the upper level is well advanced.




Week of November 1 - Framing on the upper level is well advanced

 

14-Week9

Week of November 9 - Upper level elevator entrance (shaft complete) (November 12th)

 

15-Week9b

Week of November 9 - Installing the last framing section for the upper level (November 12th)

 

16-Week11a

Week of November 16 - Building the retaining wall

 

17-Week12

Week of November 30 - Joists are up and most of the roof sheeting

 

18-Week16d

Week of December 21

 

19-week16a

Week of December 21, 2009

 

20-Week18

Week of January 4, 2010 - New doors installed

 

21-Week20

Week of January 18, 2010 - Brickwork completed

 

22-Week21

Week of January 25, 2010 - Don Runions working on insulation

 

23-week24

Week of February 15, 2010 - The drop ceiling in the narthex is removed

 

24-week26c

Week of February 28, 2010 - The narthex has been drywalled

 

25-week26b

 

26-week26a

Week of February 28, 2010 - Kitchen cabinets installed in the new addition basement

 

27-PalmSunday1

Isla Vanstone christened the new elevator during the 'unofficial' opening on Palm Sunday, March 27, 2010. The Junior Choir gave her a warm welcome on the 2nd floor.

 

28-PalmSunday2

Doug Hallman, Heather Hare and Marion Leonard cut the cake to celebrate the 'unofficial' opening of the new addition on Palm Sunday, March 27, 2010

 

29-OpenHouse-Welcome

On Saturday October 16, our Apple Fest and Open House celebrated the project completion with special guests Manitou Conference President Rev. Dr. Judith Visser, Sudbury Mayor John Rodriguez, Ward 10 Councillor Frances Caldarelli and construction manager Charlie Thomas. The afternoon event included a short official opening, delicious desserts in the Apple Café, slide shows and entertainment, a wood workshop for children and tours of the new facilities for the congregation and friends from the neighbourhood.

 

30-DSCN4532

Official Opening – October 16

 

31-WorkshopActivity

Official Opening – October 16

 

 

 

 